Details
-
Type:
Improvement
-
Status: Closed (View Workflow)
-
Priority:
Minor
-
Resolution: Done
-
Affects Version/s: None
-
Fix Version/s: None
-
Labels:None
-
Story Points:1
-
Sprint:Spring 1 : 25 Dec to 17 Jan, Spring 2 : 20 Jan to 31 Jan, Spring 3 : 3 Feb to 14 Feb, Spring 3 : 17 Feb to 28 Feb, Spring 4 : 2 Mar to 13 Mar
Attachments
Activity
| Field | Original Value | New Value |
|---|---|---|
| Epic Link |
|
| Sprint | Spring 1 : 25 Dec to 17 Jan [ 84 ] |
| Status | To-Do [ 10305 ] | In Progress [ 3 ] |
| Status | In Progress [ 3 ] | Needs 1st Level Review [ 10005 ] |
| Assignee | Karthik Raveendran [ karthik ] |
| Sprint | Spring 1 : 25 Dec to 17 Jan [ 84 ] | Spring 1 : 25 Dec to 17 Jan, Spring 2 : 20 Jan to 31 Jan [ 84, 85 ] |
| Rank | Ranked higher |
| Sprint | Spring 1 : 25 Dec to 17 Jan, Spring 2 : 20 Jan to 31 Jan [ 84, 85 ] | Spring 1 : 25 Dec to 17 Jan, Spring 2 : 20 Jan to 31 Jan, Spring 3 : 3 Feb to 14 Feb [ 84, 85, 86 ] |
| Rank | Ranked higher |
| Assignee | Chaitanya Kintali [ chaitanya ] |
| Sprint | Spring 1 : 25 Dec to 17 Jan, Spring 2 : 20 Jan to 31 Jan, Spring 3 : 3 Feb to 14 Feb [ 84, 85, 86 ] | Spring 1 : 25 Dec to 17 Jan, Spring 2 : 20 Jan to 31 Jan, Spring 3 : 3 Feb to 14 Feb, Spring 3 : 17 Feb to 21 Feb [ 84, 85, 86, 87 ] |
| Rank | Ranked higher |
| Assignee | Chaitanya Kintali [ chaitanya ] | Karthik Raveendran [ karthik ] |
| Status | Needs 1st Level Review [ 10005 ] | First Level Review in Progress [ 10301 ] |
| Status | First Level Review in Progress [ 10301 ] | To-Do [ 10305 ] |
| Assignee | Karthik Raveendran [ karthik ] |
| Sprint | Spring 1 : 25 Dec to 17 Jan, Spring 2 : 20 Jan to 31 Jan, Spring 3 : 3 Feb to 14 Feb, Spring 3 : 17 Feb to 28 Feb [ 84, 85, 86, 87 ] | Spring 1 : 25 Dec to 17 Jan, Spring 2 : 20 Jan to 31 Jan, Spring 3 : 3 Feb to 14 Feb, Spring 3 : 17 Feb to 28 Feb, Spring 4 : 2 Mar to 13 Mar [ 84, 85, 86, 87, 89 ] |
| Rank | Ranked higher |
| Status | To-Do [ 10305 ] | In Progress [ 3 ] |
| Status | In Progress [ 3 ] | Needs 1st Level Review [ 10005 ] |
| Assignee | Karthik Raveendran [ karthik ] |
| Status | Needs 1st Level Review [ 10005 ] | First Level Review in Progress [ 10301 ] |
| Status | First Level Review in Progress [ 10301 ] | Ready for Pull Request [ 10304 ] |
| Status | Ready for Pull Request [ 10304 ] | Pull Request Submitted [ 10101 ] |
| Status | Pull Request Submitted [ 10101 ] | Reviewing Pull Request [ 10303 ] |
| Status | Reviewing Pull Request [ 10303 ] | Merged Needs Testing [ 10002 ] |
| Status | Merged Needs Testing [ 10002 ] | Post-merge Testing In Progress [ 10003 ] |
| Resolution | Done [ 10000 ] | |
| Status | Post-merge Testing In Progress [ 10003 ] | Closed [ 6 ] |
Up for discussion: The copy path right-click option copies the assumed public path to the file. I think this is confusing, as within the manage link right-panel we refer to it as the public link. I think the copy path right-click option should copy the CyVerse file path, i.e., what is shown in the analysis menu. Or maybe we should just get rid of it since it is confusing.
*If the CyVerse endpoint returned the list of public files/folders then I think it would be good to have a "Copy public link" right click option. This option would be enabled for files that are public, greyed out for files that are private. However, until the file/folder public status is returned via the endpoint, let's hide the copy path option.