Description
Now that IGB version 9.1.4 is released, we need to update IGB POM versions to 9.1.6 on the master branch.
See linked issue for how to do it.
Also, check commits around the time linked issue IGBF-2196 was addressed just in case the documentation on what needs to be changed is incomplete. This is because you might need to modify files other than the POMs, such as:
- Install4J configuration file
- bitbucket pipeline file
Note: Skipping 9.1.5 in case we need to do a minor bug fix release from release branch release-9.1.4
Attachments
Issue Links
Activity
Ann Loraine
created issue -
Ann Loraine
made changes -
Field | Original Value | New Value |
---|---|---|
Epic Link | IGBF-1531 [ 17617 ] |
Ann Loraine
made changes -
Ann Loraine
made changes -
Rank | Ranked higher |
Ann Loraine
made changes -
Description |
Now that IGB version 9.1.4 is released, we need to update IGB POM versions to 9.1.6 on the master branch.
See linked issue for how to do it. Also, check commits around the time linked issue * Install4J configuration file * bitbucket pipeline file |
Now that IGB version 9.1.4 is released, we need to update IGB POM versions to 9.1.6 on the master branch.
See linked issue for how to do it. Also, check commits around the time linked issue * Install4J configuration file * bitbucket pipeline file *Note*: Skipping 9.1.5 in case we need to do a minor bug fix release from release branch release-9.1.4 |
Pooja Nikhare (Inactive)
made changes -
Assignee | Pooja Nikhare [ pooja.nikhare ] |
Pooja Nikhare (Inactive)
made changes -
Status | To-Do [ 10305 ] | In Progress [ 3 ] |
Pooja Nikhare (Inactive)
made changes -
Status | In Progress [ 3 ] | Needs 1st Level Review [ 10005 ] |
Pooja Nikhare (Inactive)
made changes -
Assignee | Pooja Nikhare [ pooja.nikhare ] |
Ann Loraine
made changes -
Status | Needs 1st Level Review [ 10005 ] | First Level Review in Progress [ 10301 ] |
Ann Loraine
made changes -
Assignee | Ann Loraine [ aloraine ] |
Ann Loraine
made changes -
Status | First Level Review in Progress [ 10301 ] | Ready for Pull Request [ 10304 ] |
Ann Loraine
made changes -
Assignee | Ann Loraine [ aloraine ] | Pooja Nikhare [ pooja.nikhare ] |
Pooja Nikhare (Inactive)
made changes -
Status | Ready for Pull Request [ 10304 ] | Pull Request Submitted [ 10101 ] |
Ann Loraine
made changes -
Status | Pull Request Submitted [ 10101 ] | Reviewing Pull Request [ 10303 ] |
Ann Loraine
made changes -
Assignee | Pooja Nikhare [ pooja.nikhare ] | Ann Loraine [ aloraine ] |
Ann Loraine
made changes -
Status | Reviewing Pull Request [ 10303 ] | Merged Needs Testing [ 10002 ] |
Ann Loraine
made changes -
Status | Merged Needs Testing [ 10002 ] | Post-merge Testing In Progress [ 10003 ] |
Ann Loraine
made changes -
Resolution | Done [ 10000 ] | |
Status | Post-merge Testing In Progress [ 10003 ] | Closed [ 6 ] |
Ann Loraine
made changes -
Assignee | Ann Loraine [ aloraine ] | Pooja Nikhare [ pooja.nikhare ] |
Ann Loraine
made changes -
Summary | Increase IGB version to 9.1.6 from 9.1.4 | Increase IGB version from 9.1.4 to 9.1.6 |
Ann Loraine
made changes -