Details
-
Type:
Task
-
Status: Closed (View Workflow)
-
Priority:
Major
-
Resolution: Done
-
Affects Version/s: None
-
Fix Version/s: None
-
Labels:None
-
Story Points:3
-
Epic Link:
-
Sprint:Fall 4 Oct 26 - Nov 6, Fall 5 Nov 9 - Nov 20, Fall 6 Nov 30 - Dec 11
Description
Situation: The Upload by URL option under the +New button in BioViz Connect does not appear to be wired up.
Task: Implement the Upload by URL functionality so that a user can enter a URL and the file will be uploaded to their current BioViz Connect page.
Attachments
Issue Links
- relates to
-
IGBF-2076 Implement File Upload
-
- Closed
-
Activity
| Field | Original Value | New Value |
|---|---|---|
| Epic Link | IGBF-2376 [ 18533 ] |
| Status | To-Do [ 10305 ] | In Progress [ 3 ] |
| Assignee | Karthik Raveendran [ karthik ] |
| Sprint | Fall 4 Oct 26 - Nov 6 [ 107 ] | Fall 4 Oct 26 - Nov 6, Fall 5 Nov 9 - Nov 20 [ 107, 108 ] |
| Rank | Ranked higher |
| Status | In Progress [ 3 ] | Needs 1st Level Review [ 10005 ] |
| Status | Needs 1st Level Review [ 10005 ] | First Level Review in Progress [ 10301 ] |
| Status | First Level Review in Progress [ 10301 ] | Ready for Pull Request [ 10304 ] |
| Status | Ready for Pull Request [ 10304 ] | Pull Request Submitted [ 10101 ] |
| Assignee | Karthik Raveendran [ karthik ] | Nowlan Freese [ nfreese ] |
| Status | Pull Request Submitted [ 10101 ] | Reviewing Pull Request [ 10303 ] |
| Status | Reviewing Pull Request [ 10303 ] | Merged Needs Testing [ 10002 ] |
| Status | Merged Needs Testing [ 10002 ] | Post-merge Testing In Progress [ 10003 ] |
| Assignee | Nowlan Freese [ nfreese ] | Karthik Raveendran [ karthik ] |
| Status | Post-merge Testing In Progress [ 10003 ] | To-Do [ 10305 ] |
| Status | To-Do [ 10305 ] | In Progress [ 3 ] |
| Status | In Progress [ 3 ] | Needs 1st Level Review [ 10005 ] |
| Assignee | Karthik Raveendran [ karthik ] | Nowlan Freese [ nfreese ] |
| Status | Needs 1st Level Review [ 10005 ] | First Level Review in Progress [ 10301 ] |
| Assignee | Nowlan Freese [ nfreese ] | Karthik Raveendran [ karthik ] |
| Status | First Level Review in Progress [ 10301 ] | Ready for Pull Request [ 10304 ] |
| Status | Ready for Pull Request [ 10304 ] | Pull Request Submitted [ 10101 ] |
| Status | Pull Request Submitted [ 10101 ] | Reviewing Pull Request [ 10303 ] |
| Status | Reviewing Pull Request [ 10303 ] | To-Do [ 10305 ] |
| Status | To-Do [ 10305 ] | In Progress [ 3 ] |
| Sprint | Fall 4 Oct 26 - Nov 6, Fall 5 Nov 9 - Nov 20 [ 107, 108 ] | Fall 4 Oct 26 - Nov 6, Fall 5 Nov 9 - Nov 20, Fall 6 Nov 23 - Dec 4 [ 107, 108, 109 ] |
| Rank | Ranked higher |
| Status | In Progress [ 3 ] | Needs 1st Level Review [ 10005 ] |
| Assignee | Karthik Raveendran [ karthik ] |
| Assignee | Nowlan Freese [ nfreese ] |
| Status | Needs 1st Level Review [ 10005 ] | First Level Review in Progress [ 10301 ] |
| Assignee | Nowlan Freese [ nfreese ] | Karthik Raveendran [ karthik ] |
| Status | First Level Review in Progress [ 10301 ] | Ready for Pull Request [ 10304 ] |
| Status | Ready for Pull Request [ 10304 ] | Pull Request Submitted [ 10101 ] |
| Status | Pull Request Submitted [ 10101 ] | Reviewing Pull Request [ 10303 ] |
| Status | Reviewing Pull Request [ 10303 ] | Merged Needs Testing [ 10002 ] |
| Status | Merged Needs Testing [ 10002 ] | Post-merge Testing In Progress [ 10003 ] |
| Resolution | Done [ 10000 ] | |
| Status | Post-merge Testing In Progress [ 10003 ] | Closed [ 6 ] |